How long does dry lining take to install?
Typical Gillingham installation times for September 2026:
- Single room (walls + ceiling, ~12-20 m²): 2-3 days install + 1-2 days jointing/skim - Three-bed terrace (whole house, ~80-120 m² wall area): 5-8 working days - Gillingham apartment (full re-line, 60-80 m²): 4-6 days - Commercial office fit-out (200 m²): 1-2 weeks - Large commercial (500-1,000 m²): 2-4 weeks - HMO conversion (4-6 bed): 1-2 weeks
Programme depends on access (lift availability in Gillingham tower blocks can be a constraint), plasterboard delivery (next-day from Travis Perkins Medway or CCF Medway), and any required electrical/plumbing first-fix.
We provide a written programme with every quote.